What are the general requirements for an Engineering Construction Permit?

All necessary requirements and procedural information to apply for a construction permit with the Public Works Department is attached to the Construction Permit Application form. A quick rundown of the necessary requirements applicants must provide are as follows:

  • The Engineers Cost for all public improvements.
  • A completed Construction and Street/Lane Closure Application.
  • A list of contractors who will be performing any work in the public right-of-way.
  • A current Certificate of Insurance for contractors performing any public improvements with the City listed as ‘additional insured.’
  • Proof of a valid/current City Business License for each contractor.
  • A site and job specific Traffic Control Plan for review and approval.
  • Material submittals such as asphalt, concrete, sewer pipe/manhole, storm drainpipe/manhole, trench bedding, striping, etc.

**Please note that processing for an application may take up to 10-days on a 4/10 work schedule, or 2 1/2 weeks.